There were all sorts of proposals during the recent election campaign. And promises too. From those that all previously contracted obligations would be honoured, to those concerning the cancellation of the EXPO 2027 project. Truth be told, promises about cancelling the international exposition were heard from one of the opposition parties, but not from representatives of the Student List.
Guided by the principle “what is good we will keep, what is bad we will fix, what is missing we will build”, a phrase uttered during the campaign by Academician Radomir Saičić from the Students Win list, we analysed what the future might hold for three major infrastructure projects in Serbia. Projects whose cost is measured in billions of euros… And which have, in the meantime, become several times more expensive than their originally contracted or announced price.
Marko Milanović, from the Fiscal Council of Serbia, analyses three projects for Forbes Serbia – the Morava Corridor, the construction of the Đerdap 3 reversible hydroelectric power plant, and the Belgrade–Zrenjanin–Novi Sad highway.
Will anything change with the arrival of a new government? Can it, and should it? Why have these projects become so much more expensive, and what is the actual price of the state’s own unpreparedness?
Three projects and three examples of differing price increases
When it comes to major capital projects, especially those whose value is measured in billions of euros of taxpayers’ money, it is vital to track the entire investment cycle. That is, the evolution from initial estimates and the selection of the design solution, through document preparation and contracting, to the execution of works, changes to deadlines, and final costs, says Milanović.
He adds that an analysis of the three largest individual state investments – the Morava Corridor, the Belgrade–Zrenjanin–Novi Sad motorway, and the Đerdap 3 reversible hydroelectric plant—shows certain common characteristics that may point to serious systemic weaknesses in the planning and management of public investments.
Morava Corridor: contracting prior to complete project development
Preparations for the implementation of the Morava Corridor began well before the signing of the commercial contract. In February 2017, the Government of Serbia formed a working group for the implementation of the project with companies Bechtel and Enka. In September 2018, a Memorandum of Understanding was signed between Serbia and the US in the field of infrastructure cooperation. At that stage, the first projected value of the project appeared, standing at around 800 million euros.
The project was subsequently recognized by a Government decision as a project of special importance. In July 2019, a special law was adopted establishing a special legal regime for its execution. This included deviations from regular contractor selection procedures and certain steps in project preparation and delivery.
“The commercial contract accepted a value of 943 million euros, which already represented an increase of nearly 18 per cent compared to the previously stated target value of 800 million euros. However, the problem is that even those 943 million euros did not necessarily represent the final price. In certain official documents, the planned value was presented as 943 million euros plus additional costs, whilst for specific works, such as the regulation of the West Morava riverbed, unit price calculations were stipulated,” Milanović explains.
This raises the question of how the initial value was formed in the first place, on the basis of what level of detail in the design documentation, and how well the actual scope and costs of all necessary works were known at the time of contracting.
Price doubling
According to data from the Fiscal Strategy, our interviewee recalls, the estimated value of the project reached approximately 252 billion dinars in 2026, or around 2.1 billion euros. That is more than double the originally accepted contract value. And approximately 2.6 times more than the initial target estimate from 2018. Furthermore, it is far from certain that this will be the final cost of the project.
“In public explanations, the contractor cited the escalation clause, the pandemic, and the war in Ukraine. Such clauses do indeed exist in international construction practice and are not contentious in themselves. However, their existence does not automatically explain an increase in the total project value of over one billion euros,” warns Milanović.
Taxpayers will foot the bill for this venture. Serbia, it should be remembered, took out loans on four separate occasions with foreign banks to finance this motorway.
Milanović says that the Morava Corridor is in its final phase, with physical completion exceeding 92 per cent. As such, there is no scope for fundamental changes. “However, it presents an ideal opportunity to thoroughly analyse the objective circumstances, potential oversights, and key bottlenecks that led to such a drastic increase in costs, and to present the findings of that analysis publicly as lessons for future projects.”
Belgrade – Zrenjanin – Novi Sad: from conceptual changes to phased contracting
The Belgrade–Zrenjanin–Novi Sad project faces a somewhat different problem, but one that is potentially just as significant.
“Initial plans actually envisaged the construction of an express dual carriageway rather than a full motorway. According to 2018 documentation from the Ministry of Construction, the estimated value for the Zrenjanin–Čenta–Belgrade (Borča) section was around 110 million euros, with an additional 100 million euros for the Zrenjanin–Novi Sad route. So, at the time, people were talking about a project worth approximately 210 million euros,” Milanović recalls.
“It is important to emphasise that this estimate is not directly comparable to the later contracted price, as the entire concept of the project was changed in the interim. This includes both the category of the road and its technical scope. But it is precisely this change that opens up an important economic question: on the basis of what analyses was the decision made to build a significantly more expensive motorway instead of an express road? And was that decision based on a proper analysis of traffic demand, costs, and benefits?”
From 200 million to 1.6 billion euros
In January 2021, the Government declared this a project of special importance via a formal conclusion. Although no special law was passed as in the case of the Morava Corridor, special procedures provided under the legal framework of the time for linear infrastructure projects were applied.
“The commercial contract for design and construction was signed in November 2023 with a contracted value of nearly 1.6 billion euros excluding VAT. The new project covers the construction of a 105 km motorway, as well as additional infrastructure, including a parallel non-commercial road on the Žabalj–Novi Sad route,” Milanović notes.
“The manner in which the contract was subsequently developed is particularly interesting. This was not the case with the Morava Corridor. In September 2024, an addendum was concluded modifying the contractor’s payment terms. Then, in May 2025, a specific addendum to the framework commercial contract was signed, defining six project phases in terms of their value and scope of works. In the same month, an addendum was also signed regulating the funding and scope of the first phase. In a report from October 2025, addenda for other phases that were still in preparation were also listed,” says Milanović.
Đerdap 3 Pumped-Storage Plant: surge in estimated value prior to implementation
Đerdap 3 is a project intended for realization under the Serbian-American agreement on energy cooperation. Thanks to this, it is exempt from standard public procurement regulations. The invitation to serve as strategic partners to the state was extended at the time exclusively to American companies. Only Bechtel responded. According to the latest information, the Working Group is reviewing that offer. It is not known whether anything official has been signed yet. Recently, however, a contract was signed with a consortium led by the Jaroslav Černi Institute for the development of spatial plans and part of the technical documentation.
“Đerdap 3 is currently at the stage of technical design documentation. That is precisely why it makes an interesting comparison with the previous two projects, as it allows potential risks to be assessed before the state enters the heavy construction phase,” says Milanović.
According to planning documents from 2023, the estimated project value was approximately 1.4 billion euros. However, just two years later, in May 2025, the official estimate rose to roughly 2.6 billion euros. This represents an increase of around 86 per cent, even though the project has not yet entered the construction phase where typical additional works might arise.
Project complexity as a distinct test
“With Đerdap 3, the fact that this is a technically highly complex energy project is particularly important. Costs here depend on numerous factors: geological and hydrological conditions, the design of underground facilities and reservoirs, power equipment, grid connection, and financing terms,” our interviewee says, adding:
“Furthermore, the economic viability of a pumped-storage hydroelectric plant cannot be viewed solely through construction costs. It is necessary to evaluate its role in the power grid, future energy storage needs, expected revenues, and systemic benefits, as well as alternative ways of providing power grid flexibility.”
A systemic issue in investment preparation, contracting, and oversight
“The examples of these three projects raise broader questions about how the state prepares, implements, and monitors major public investments. Four interconnected issues stand out in this process. First is the exemption of the largest projects from standard procedures meant to ensure cost control. Secondly, the shortening of the preparatory phase and the transfer of insufficiently assessed risks into the construction stage. The third problem is taking on major contractual commitments before key project elements are adequately developed. And finally, a lack of transparency in explaining the reasons for subsequent value increases. These are often explained in vague terms by rising prices for materials and labour, even though the orders of magnitude are such that it is unlikely to be the sole reason,” says Milanović.
The Morava Corridor is a classic example of the first issue.
The passage of the special law in 2019 allowed for contracting outside the standard public procurement framework. In doing so, the state relinquished competitive price checks and part of the usual control mechanisms for subsequent contract variations. This practice was later widely expanded: in 2020, a lex specialis was passed for linear infrastructure projects, including roads, railways, and municipal infrastructure, whilst following its repeal in 2023, a special contracting regime was established for EXPO and associated projects.
“The problem, therefore, is not just that the estimated values of projects rise drastically, but that the public lacks sufficient information to determine why this happens. For all the projects mentioned, it remains unknown how much of the increased value is a result of inflation, how much stems from additional works, and how much from modifications to the original design. This does not mean that all additional costs are unjustified, but it does mean that their justification is far harder to verify independently. Paradoxically, for the very largest and financially riskiest investments, the state has chosen to deviate from the procedures that ought to ensure the strictest control over the spending of public money,” warns Milanović.
Inflation cannot be a universal explanation for rising costs
Rising prices for construction materials, supply chain disruptions during the pandemic, and the consequences of the war in Ukraine have indisputably impacted the construction industry. However, this does not mean that every increase in the value of infrastructure projects can be attributed to inflation.
“International construction contracts often contain escalation clauses that adjust agreed prices to reflect cost changes. But an increase in the price of steel or cement does not automatically mean that the total value of a motorway increases by the exact same percentage.”
“If inflation were truly the main driver behind the drastic surge in the value of infrastructure works in Serbia, that should be relatively easy to document and present to the public through an overview of applied indices, contract formulas, and calculated figures. However, such a detailed breakdown has not been made public. Therefore, the question remains open as to what contributed to the cost increases and to what extent. For multi-billion-euro projects, pointing to inflation is far too general a statement and cannot serve as a substitute for a transparent financial accounting,” Milanović concludes.
(Forbes Serbia, 29.10.2026)