The Novi Sad rail station canopy collapse was also contributed to by systemic shoddiness

By Ognjen Radonjić, Professor at the Faculty of Philosophy, University of Belgrade

and

Vladimir Obradović, Professor at the Faculty of Organisational Sciences and a member of the Inquiry Commission

Fifteen days before the presidential and parliamentary elections, Aleksandar Vučić travelled by train to Novi Sad with Hungarian Prime Minister Viktor Orbán on 19 March 2022. The railway line was presented to the public as a major completed state project, and the railway station as fully reconstructed. Documentation, however, shows that in December 2021, technical departments had been warning about unfinished works, postponed testing and deadlines that were at odds with the requirements of the investor and the head of the President’s Cabinet.

Even 23 months after the collapse of the canopy, which killed 16 people and seriously injured one person, no court proceedings had yet begun. In the meantime, the Inquiry Commission obtained new correspondence and minutes from January 2022 showing how the station was being prepared for passengers and who was involved in decisions to open it before the elections. Instead of adjusting the opening date to the actual state of the railway line and station, project participants were being asked to fit the works and testing into an ever-shorter timeframe. Representatives of the Presidency were involved in communications about delays, as well as in correspondence concerning works to prepare the station to receive passengers. The documents make it possible to trace the transition from pressure to speed up the works to a plan to make the station look ready for opening, even though some of the designed solutions were being left for later.

To shorten the deadlines, four planned railway tests were skipped

Following a meeting held on 19 January 2022, Jelena Popović, chief coordinator for international affairs at Serbian Railways Infrastructure, circulated the minutes to participants the following day and asked them to submit their comments in a separate document. The email subject clearly stated that the meeting was devoted to coordinating the activities of the Chinese and Russian contractors.

The email was sent to a wide range of participants from Serbian Railways Infrastructure, the Ministry of Construction, Transport and Infrastructure, technical supervision, companies involved in the works, the Chinese consortium, as well as Nataša Vukšić from the General Secretariat of the President of the Republic.

Her presence in this correspondence and at the meeting once again confirms that the Presidency was involved in coordinating and managing the project during its operational phase, at a time when testing results, delays and the conditions for putting the railway line into operation were being discussed.

The minutes state that dynamic testing had begun the previous day, 18 January, with an inspection of the entire route up to kilometre 74. It included checks of the track, the overhead contact system and the radio system used for communication between train drivers and railway traffic control centres – the GSM-R communications system, which is important for railway operations and the safe exchange of data.

The minutes note that the required standards for the track had not been fully achieved, but that, in the participants’ assessment, the deviations nevertheless allowed testing to continue. At the same time, an analysis of the condition of the overhead contact system was still under way in Munich, and the official report was still awaited. In other words, at the time of the meeting, not all the final findings on the condition of the systems being tested were available.

The most telling detail concerns the GSM-R testing. Of the six planned runs on 18 January, only two were carried out. The minutes present this fact in a favourable light, stating that the results were “highly positive” and thanking the Chinese partners and technical supervision for enabling the tests despite “very unfavourable conditions”. However, two completed runs were not six planned runs. Four tests scheduled for that day were not carried out, while the official reports that were supposed to confirm the status in question were still awaited.

Under such circumstances, it is not justified to present two successfully completed tests as a full substitute for the six planned tests. The minutes also acknowledge that working conditions were unfavourable, that certain track standards had not been fully achieved, and that the results of the overhead contact system analysis were not yet available. Instead of completing the testing according to the established plan and then deciding on the next steps on the basis of complete and officially confirmed findings, the process continued under deadline pressure.

The minutes also show that the problems were not limited to railway testing. The Ministry of Construction, Transport and Infrastructure reported that work on the underpass in Kisačka Street was progressing, but that it was questionable whether the load testing would be completed by 20 February. The final week of February was cited as a more realistic deadline. At Novi Sad station, work on the tracks and the resolution of technical problems were still under way. Here too, a delay compared with the original 20 February deadline was recorded, with an assessment that the work might only be completed by the end of the month. Despite this, the Chinese contractor was asked, in coordination with the Ministry, to draw up a crisis action plan, while Deputy Minister Anita Dimoski was supposed to assist with coordination with Serbian subcontractors.

A crisis action plan to make up the delays at any cost

Thus, despite unfinished works, postponed deadlines and testing that had not yet been completed, the Chinese contractor was asked to prepare a crisis action plan. In project management, such a plan can be a justified response to delays. Its purpose, however, must be to establish how a project can be completed while preserving all technical and safety requirements, rather than how to meet a politically imposed deadline at any cost. The minutes show that, ahead of the planned opening of the railway line, the contractor was being asked to find a way of making up the accumulated delays at any cost.

Eight days after the meeting at which the Chinese contractor was asked to prepare a crisis plan, the chronology entered a new phase. The focus was no longer on completing the railway line, but on preparing Novi Sad station to receive and dispatch passengers. On 27 January, Milan Banović, a representative of the CRIC-CCCC consortium, sent a list of work items that the Chinese contractor proposed carrying out for the reception and dispatch of passengers at Novi Sad station. In an email addressed to Anita Dimoski, managers of Serbian Railways Infrastructure, representatives of Novi Sad, domestic subcontractors and other project participants, as well as Nataša Vukšić, he said he was sending the document in preparation for a meeting scheduled for 28 January at 2 pm.

The following day, 29 January, Banović sent the same recipients a similar document, an updated overview of the works for the first phase at Novi Sad station. In the email, he explicitly stated that he was sending the revised list on the basis of the previous day’s meeting.

Attached to the first email, Banović sent a table titled Works for the Reception and Dispatch of Passengers at Novi Sad Station, which the CRIC-CCCC consortium representative had submitted on 27 January as a proposal for the first phase of works. In the second email, sent the day after the meeting, on 29 January, he sent an updated version. The table shows side by side what the contractor proposed should be done, who was entrusted with individual tasks, and what the project had actually envisaged.

The comparison shows that the aim was not to complete the station in full according to the design, but to make it operational and present it as ready to receive passengers as quickly as possible. In other words, the contractor proposed a series of temporary and superficial interventions instead of certain designed solutions, and the proposal was discussed with representatives of the competent institutions and domestic subcontractors, while the updated overview was also sent to Nataša Vukšić from the Presidency, which had no formal jurisdiction over the project. It can therefore be argued that the contractor proposed deviations at the expense of quality and safety, and that the Serbian side approved them.

The table of proposed works at Novi Sad station shows how it was being prepared for use while certain designed solutions remained unimplemented. The table lists the planned interventions, subcontractors and notes on what the design had envisaged. It is precisely the comparison of these columns that reveals the difference between an actual reconstruction and works intended to bring the station into a condition suitable for public presentation.

All show on the outside, misery within

The difference begins with an apparently ordinary cleaning job. Item 3 specifies the cleaning and washing of all glass surfaces, covering approximately 600 square metres. The note warns that the glass cannot be completely cleaned because of years of accumulated pigeon droppings. This was not a trace of a problem that had arisen immediately before the opening, but a visible consequence of the station’s long-term neglect. At the same time, the document states that the City of Novi Sad should install banners on certain glass surfaces to conceal the stains, even though the project envisaged the complete replacement of the glass façade.

Item 4 provides for the cleaning and washing of the canopy at the main entrance, but only the upper section “visible from the terrace”. This wording reveals the logic behind the entire list of works. What mattered was not that the canopy should be cleaned in its entirety, but that the visible part should be clean. Just as the stained glass was washed and partly concealed by banners, attention here too was focused on what passengers and visitors would be able to see. Instead of addressing the consequences of years of inadequate maintenance, the appearance of the station was being tidied up. It was the logic of a Potemkin village.

A similar distinction between a temporary and a designed solution appears in item 8. While the new doors envisaged in the project were awaiting a new structure, the “solution” was reduced to repairing two entrance sensor doors. The lighting issue was dealt with according to the same model. Under the design, item 13 provided for new lighting to be installed in a suspended ceiling, but this was subsequently abandoned and it was proposed that the lights be installed in the existing space.

Even more striking are items 14 and 15, which provided for adding missing red mosaic tiles and marble slabs in the vestibule and on the gallery, followed by painting them. Both entries carry a note stating that the project envisaged replacing them with new elements, while filling in and painting the existing surfaces was certainly not the same thing. This could alter the appearance and remove the most obvious signs of deterioration, but it also meant that the planned refurbishment had not been carried out.

What was planned and what was actually done in the reconstruction of the canopy

For the canopy itself, however, the most important is item 16, concerning the refurbishment of the ceiling of the canopy at the entrance to the building. The works listed included removing the red mosaic tiles, applying filler and painting the surface to match the existing condition. The note, however, states that the project envisaged structural rehabilitation of the slab and the complete replacement of the mosaic tiles.

That difference requires particular explanation. The document records work on the canopy while simultaneously indicating that the designed solution was not identical to the intervention described. It is therefore essential to establish exactly what was carried out, whether and how the slab was repaired, who ordered and supervised the works, and on what basis the space beneath the canopy was opened for public use. At the same time, given Nataša Vukšić’s role throughout this process, it is clear that President Aleksandar Vučić must have known that the canopy had been reconstructed, despite his claims to the contrary.

Serbian officials and Chinese contractors at the opening of the renovated railway station in Novi Sad

The table is also important because it names the contractors directly responsible for individual works. They include several domestic subcontractors, among them Frigo Žika, Aladin and Starting. When this information is considered alongside the project’s contractual structure, the distinction between the formal levels of contracting and the companies entrusted with specific works at the station becomes apparent. Above the domestic contractors were the Chinese consortium CRIC-CCCC and Chinese subcontractors, including CCECC Balkan. According to this table, the work on the building cannot be described as a job carried out by Chinese companies; rather, it appears that the Chinese companies, like a pass-through boiler, charged a commission, thereby increasing costs. The same mechanism can be seen in the “other works” item in annexes 2, 3 and 4.

It is particularly striking that the City of Novi Sad also appears in the table alongside domestic companies. The city authorities, therefore, were not merely observers of the project but are listed in this overview in connection with specific works at the station. This gives additional weight to documentation previously reported by Radar, according to which then-mayor Miloš Vučević and City Council member Adrijana Mesarović were receiving information as early as December 2021 about unfinished works and deadlines for the opening of the railway line. The Novi Sad government thus appears both in the records of work at the station and in correspondence concerning the state of the project.

That this approach continued after the January meetings is shown by the minutes of a meeting held on 9 February 2022. Nataša Vukšić was again among the participants, listed as a representative of the Cabinet. An inspection of the route was also carried out that day. Regarding the station building in Novi Sad, the note records that its appearance was praised, while technical supervision was not due to submit its report on the state of works in the various professional fields until 11 February. Praise for the appearance, therefore, was not confirmation that the station had been completed according to the design, properly and safely. It was an assessment of the impression made by the building during the inspection.

The documents from January 2022 therefore show a model of project management in which the opening deadline was not adjusted to the state of the works; instead, participants were required to adjust the works to the deadline. While testing continued despite deviations and without all the final reports being available, a list of interventions was drawn up for the station that would, at least on paper, make it capable of receiving passengers and ready for public presentation. When a political deadline becomes more important than the actual condition of a building, and temporary interventions create the appearance of a completed reconstruction, the boundary between what was done and what was merely presented as having been done becomes a matter of safety.

The item concerning the canopy ceiling makes that question immediate. What was actually carried out on it? What remained of the planned structural rehabilitation? And who certified that the space beneath it was safe to use? Without answers to these questions, it is impossible to understand the full responsibility for the tragedy in which sixteen people were killed and one person seriously injured.

(Radar, 08.10.2026)