The Čoka Rakita gold project in the Crni Vrh area near Žagubica is entering its final development phase, and a new feasibility study by DPM Metals (formerly Dundee Precious Metals) shows that this deposit could become one of the most profitable in the region.
Just a year ago, in the pre-feasibility study from December 2024, the project’s net present value (NPV) was estimated at around USD 735 million, while the new feasibility study now shows a value of USD 782 million, based on an average gold price of 1,900 dollars per ounce (approximately USD 59.1 million per tonne of gold).
However, the most dramatic part concerns the sensitivity analysis: in a scenario where the gold price would reach 3,500 dollars per ounce (USD 108.9 million per tonne of gold), the total value of the mine would practically triple, to around USD 2.2 billion, the company announced.
Thus, in a conservative scenario, the mine remains highly profitable. In an optimistic scenario, the economic value of the project practically explodes, and Čoka Rakita could rank among the most profitable mines in the region, and even in Europe.
The latest study includes estimates that the mine will produce around 41 tonnes of gold during its projected ten-year lifespan, compared with the previous preliminary estimate of around 37 tonnes. Average annual production is forecast at around 4.6 tonnes of gold, including approximately 5.9 tonnes annually during the first five years.
Naturally, initial capital costs have also risen, amounting to USD 448 million in the new scenario (more than the previously estimated USD 379 million from the pre-feasibility study).
According to the current project timeline, as stated by DPM, construction of the mine should begin in early 2027, and the first ore processing is expected in the first half of 2029. When operations reach full capacity, the project is expected to provide around 500 jobs – including direct employment in mining and processing, as well as indirect engagement through subcontractors, logistics, service companies and local suppliers.
It is also noted that in mid-November this year, DPM Metals received a key regulatory document – the Decision on Determining the Scope and Content of the Environmental Impact Assessment Study. This is a mandatory step in the procedure, without which preparation of the main Environmental Impact Assessment (EIA) cannot begin.
The Čoka Rakita project is estimated at 7.34 million tonnes of ore with a grade of 6.44 g/t of gold.
(eKapija, 01.12.2025)