Even almost two years after the collapse of the canopy at Novi Sad Railway Station, no one has yet been held accountable for the deaths of 16 people and the severe injuries of another person.
Furthermore, the public does not even know whether former President Aleksandar Vučić used his final day in office to pardon any of the suspects in this tragedy. Admittedly, between 1 November 2024 and last Friday, he himself has come a long way – from claiming that “only the canopy was not reconstructed” to a pre-election message stating that “those responsible for the collapse of the canopy must be brought to justice”.
While the entire case awaits a judicial outcome and trains do not stop, but merely pass by the station in Novi Sad, much has become clearer. This is particularly true if one considers that the Commercial Agreement, concluded in 2018 by the Government of Serbia with the Chinese contractor, is the key to understanding not only the price, but also the quality, responsibility, and deadline within which the Novi Sad–Kelebija railway line should have been reconstructed, explains an expert in FIDIC contracts and infrastructure project management. His assistance is invaluable precisely because the contract is based on the FIDIC Yellow Book model for major infrastructure projects on a “design and build” basis.
In this instance, this means that the CRIC–CCCC consortium designs and executes the works, whilst also bearing responsibility for the stability and safety of the structures. Meanwhile, supervision controls the design and execution, evaluates the contractor’s claims, and manages procedures affecting deadline, price, and quality. The problem is that virtually all key provisions of the Yellow FIDIC regarding deadline and price were amended by the contract, meaning that the execution of certain works commenced when the entire project should have already been near completion.
What frequent changes to deadlines and prices reveal about project management
The Commercial Agreement originally allocated 180 working days for project design, excluding time for technical review, followed by a 33-month execution deadline. The start of this period was conditional upon the prior fulfillment of several contractual obligations, including those of the employer, the Infrastructure of Serbian Railways Company (Infrastruktura železnice Srbije), and the financier, the Ministry of Construction, Transport and Infrastructure, regarding building permits for individual sub-sections.
Although there was no predetermined completion date, it was expected that all works would be finished by the end of 2022. In April 2019, while announcing the start of works for the end of that year, the then departmental minister, Zorana Mihajlović, claimed they would be completed by “mid-2022”.
The Chinese contractors and the former Construction Minister, Zorana Mihajlović, at the inauguration of the works on Novi Sad-Subotica railroadAlthough she was the one who signed the Commercial Agreement in July 2018, and the loan agreement for the project was ratified by law in May 2019, supervision issued the notice to proceed only on 1 July 2022. At that point, according to Zorana Mihajlović, the project should have already been completed, and according to contractual calculations, was near its end. Only then did the agreed 33-month deadline begin to run, which would have expired at the end of March 2025, but was subsequently extended by five months to 31 August last year.
However, even that new deadline was not met. From the available documentation, it is unclear whether and when it was extended again, nor is there a supervision decision stating who bears the responsibility for further delays. Naturally, there is no evidence that the employer activated liquidated damages or other mechanisms to protect itself from yet another deadline overrun. Instead of acting as a robust contractual control mechanism, the deadline became a subject of negotiation between contractor, employer, and financier, which supervision subsequently formalised. Ultimately, the cost of that delay, when it generates additional expenses, is paid by the taxpayers.
How the price of the Novi Sad–Subotica railroad escalated
Under the “design and build” model, the agreed price should cover everything required for the completed structure to be fully functional. Subsequent works should be an exception, as under the contract, these are works that were neither agreed upon nor necessary, but were requested afterwards by the employer and financier.
Although the employer’s requirements contained an estimated cost of works of €681.4 million, Serbia accepted a contract price that was 46 per cent higher: $1.163 billion, or roughly €995 million. The documentation does not show who analysed this discrepancy or by what criteria, nor whether the price was “internationally competitive”, as stated in the intergovernmental agreement between Serbia and China.
Following completion of the design phase, the CRIC–CCCC consortium requested additional payment for works it deemed to be extra. According to the contract, it should have justified its request, and supervision should have evaluated its merits. Supervision reviewed the request and provided comments, but the employer, financier, and contractor subsequently agreed on 16 line items and their amounts. Following this, supervision made a final decision, and under Agreement 1, the state agreed to pay the contractor an additional $112 million.
And that was not all. The Commercial Agreement capped subsequent price increases relative to the contracted price at a maximum of 10 per cent, or approximately $116.3 million. However, Agreement 1 stipulated that the additional $112 million would not count towards that limit, thereby leaving the entire amount of roughly $116.3 million available for future increases.
Something similar indeed happened. Through Addenda 2, 3, and 4, a further $57.5 million was approved for extra works, pushing the project value up to $1.33 billion. With other approved and announced additional works, the final price could end up almost 20 per cent higher than originally agreed. Furthermore, based on the descriptions of the line items,
Radar’s interviewee notes that part of these works raises the question of whether they were already covered by the contractor’s contractual obligations and design risk. As the contract remains in force, the basis and justification for all approved increases should be re-examined, as this contradicts the agreed “design and build” model, whose chief advantage is precisely to limit subsequent price hikes.
It is for this very reason that the investigation should establish who initiated the changes to key FIDIC provisions and with what justification, as well as the grounds on which additional time and payments were granted to the contractor. This is all the more pressing given that an Inquiry Committee has since uncovered numerous emails clearly indicating that close associates of Vučić – his Chief of Staff, Ivica Kojić, and Nataša Vukšić from the General Secretariat of the Presidency – insisted on accelerating the works, even at the cost of a significant increase in expenses.
In addition to issues with contractors, quality control also failed to function as intended. Specifically, during the design phase, supervision was supposed to review and approve documentation according to the employer’s requirements, while the employer was meant to secure a statutory technical review independent of the designer. The employer initiated the selection process for an inspector, but suspended it after the CRIC–CCCC consortium announced it had already engaged the firm Cestra to conduct the review at its own expense – raising serious questions about its independence. This is further highlighted by the fact that Cestra accepted 823 design documents without objection, while the reports do not indicate whether the comments of the Revision Commission were ever resolved.
Our interviewee recalls that during 2024, two technical inspections were initiated. The first established that the Novi Sad station building was approximately 77 per cent complete, yet recommended trial operations. The second inspection had not even been concluded by 1 November, when the canopy collapsed. Neither inspection culminated in a final report, nor did the process lead to a decision on the structure’s fitness for use. Nevertheless, the station building was grandly opened twice in the presence of top state officials – on 19 March 2022 and 5 July 2024. Following the collapse, Infrastructure of Serbian Railways stated that statutory prerequisites for issuing an occupancy permit had not been met, and in January 2025 confirmed that works were still ongoing.
Neither inspection culminated in a final report, nor was an application submitted for an occupancy permit for the building, which was grandly opened twice in the presence of top state officials – on 19 March 2022 and 5 July 2024. Following the collapse, Infrastructure of Serbian Railways stated that statutory prerequisites for issuing an occupancy permit had not been met, and in January 2025 confirmed that works were still ongoing.
Between the two technical inspections, an internal handover of Block B took place. This was not a technical inspection, meaning the status of the station building as a construction site remained unchanged; the official record notes that this handover does not release the Chinese contractor from liability. Quite apart from this, it is difficult to fathom that a facility of such importance was never once inspected by the building inspectorate, which justified this by claiming it had not been notified of the completion of the foundations or the structural work of the facility, and that there had been no formal complaints.
What the contract stipulates when someone fails to do their job properly
The Commercial Agreement specifies who held which obligation and what occurs when the agreed outcome is not achieved. The contractor is responsible for design and execution, including the stability, safety, and functionality of the structure, and cannot transfer that responsibility to designers, suppliers, or subcontractors, stresses the FIDIC contract and infrastructure management expert. He emphasizes that oversight failures, or the involvement of the employer and financier in individual decisions, do not in themselves relieve the contractor of responsibility for the final technical outcome.
This makes it all the more incomprehensible why not a single representative of the CRIC–CCCC consortium has been included in any investigation into the canopy collapse. This is particularly striking given that the consortium was obligated to rectify defects for which it is contractually liable at its own expense and bring the station building to a state fit for use – yet available documentation does not indicate that it did so. On the contrary, from the outset, it disputed its own liability, citing among other things the fact that the facility had been put into service. Using the facility does not relieve the contractor of liability for defects, and the contract remains in force.
Secondly, the existing contract provides for compensation for damages. Therefore, the contractor’s third-party liability insurance should have been activated to cover compensation claims from the families of the 16 deceased and the severely injured individual, alongside the professional indemnity insurance of the supervision team. Instead of the Chinese consortium, this compensation will be paid jointly by the State of Serbia and Infrastructure of Serbian Railways as the employer. In other words, by the citizens as taxpayers.
Thirdly, Infrastructure of Serbian Railways and the ministry could have called the performance bond up to approximately $116.3 million, halted further payments, and re-examined previously approved sums. Yet they did not do so. Radar has learned that even after the canopy collapsed, the state continued to make payments for the Hungarian–Serbian railway project. On that basis, 8.3 billion dinars – or over €70 million – was paid out from the budget over the course of last year and in the first nine months of this year.
Although the contractor is primarily responsible for the technical result under the contract, responsibility for the way the control system operated is also shared by supervision, the employer, and the financier, our interviewee notes. He questions whether, if one of the country’s largest infrastructure projects was managed in this manner, this is an isolated exception or part of a broader model for managing state projects. The answer appears self-evident. Thus, the collapse of the canopy is not merely a technical incident, but the direct consequence of how this entire project was contracted, managed, and supervised.
(Radar, 23.10.2026)